L-01 · Corporate
Incorporate North 49 Shrimp Co. Ltd.
File BC Inc. articles and by-laws as a standalone CCPC. Sibling structure — no association with 1362557 B.C. Ltd. per ITA s.256 (preserves the small-business deduction).
Roadmap & milestones
Every milestone is gated on the prior. Phase 2 is not assumed — it is gated on five economic criteria. We publish what we are committing to and what we have not yet verified.
Term sheet to first chef sale
Live HOSO + Asian retail — no certification gate
To Phase 1 production at full ramp
20 Atarraya boxes, ~58,000 lb saleable Y2
Phase 2 gating criteria
All must be met before $8–12M capex commits
KILL gates in the first 180 days
CFIA pre-clearance, Costco compliance (conditional), BC MWR
Day 0 – 30
2026-06-15 to 2026-07-15
L-01 · Corporate
File BC Inc. articles and by-laws as a standalone CCPC. Sibling structure — no association with 1362557 B.C. Ltd. per ITA s.256 (preserves the small-business deduction).
L-CNSL · Corporate
Engagement letters: BC corporate counsel (incorporation + ShA); US trademark counsel (USPTO Class 29/31); Canadian-US tax counsel (sibling-CCPC opinion).
OPS-02 · Site
Licensed BC mechanical engineer heat-load + electrical-load study against shortlisted candidate shells. Gates LOI on any site. KILL condition if max-case ($379K/yr energy) confirmed against base-case capital stack.
G-RISK-01 · Operations
Specialty insurance broker engaged to scope aquaculture-mortality cover, property, GL, product recall, D&O, cyber. Y1 premium target $45–85K (12-line program).
L-09 · Licensing
Term sheet covering five mandatory asks: source-code escrow, local-mode firmware (≥72-hour autonomous), royalty step-down 8% → 5% → 3%, Canadian territorial exclusivity, improvement-IP grant-back.
L-04 · Corporate
Certified-mail voluntary disclosure of any Costco-employee equity interest to Costco Wholesale Ethics & Compliance (Issaquah). Conditional — applies only if Class B Costco-Manager tranche is reinstated; current capital stack uses VANTEC syndicate instead.
FG-01 · Capital
BCSRIF replaces the discontinued AgriInnovate as anchor instrument. Pre-consultation with DFO Pacific confirms commercial-recipient eligibility and 90% cost-share availability for the next cycle.
NEW-V-11 · Regulatory
DFO Introductions and Transfers Committee Section 56 Licence pre-consultation for non-native L. vannamei. Runs PARALLEL to CFIA Form 5670. ITC can veto even when CFIA clears on disease grounds. Budget $5K consulting biologist for escape-mitigation plan; 90–180 day total ITC review window.
Day 30 – 90
2026-07-15 to 2026-09-15
OPS-01 · Site
Avison Young / Colliers / Lee & Associates broker scout delivers three ex-cannabis M-2 industrial term sheets in Langley / Abbotsford / Surrey (food-grade fitout, 800 A 3-phase, dehumidification).
OPS-06 · Operations
Primary toll-processing relationship with Albion Fisheries (Richmond BC). Live-product Vibrio-surveillance + frozen-product CCP-5/CCP-7 both scoped.
L-08 · Corporate
Canadian Intellectual Property Office + US Patent and Trademark Office filings for the North 49 mark. Class 29 (processed seafood) + 31 (live animals) + 40 (custom processing).
DOMAIN · Corporate
Primary domain plus defensive registrations (north49.shrimp, north49-shrimp.ca, common-misspell variants).
HR-G06 · Team
Farm Manager offer issued and signed ($95–115K, M-2 critical path). Lead Aquaculture Technician offer ($32/hr + shift differential, M-1). Sourced from VIU + BCIT pipelines and net-pen-salmon operators.
HR-G03 · Team
Paid co-op pipeline with Vancouver Island University Fisheries & Aquaculture Diploma. Activated Month -6 relative to stocking.
G-5 · Sales
Vancouver white-tablecloth + Cantonese banquet + Asian retail live-tank shortlist. 5–10 in-person validation calls; 3+ written LOIs or forward-purchase intents.
V-05 · Sales
Founder writes the verbatim debrief of the Costco buyer's responses to the 10-question slate. Determines whether Phase 1 routes to Roadshow, BC-regional SKU, or Phase 2 only — reorders the next 12 months.
Day 90 – 180
2026-09-15 to 2026-12-15
OPS-03 · Site
30-day due-diligence exclusivity executed on lead ex-cannabis M-2 facility. ALR/zoning confirmed non-applicable; mech-eng study (V-01) closed before signature.
OPS-04 · Regulatory
BC Ministry of Environment pre-application meeting on the chosen site. Confirms zero-liquid-discharge + biofloc effluent treatment train is achievable inside 18 months. Stop condition if MWR pre-screen is negative.
PERMIT-BUILD · Regulatory
Municipal building permit, stormwater management plan, acoustic study for biofloc blower-load. Filed concurrently with the MWR application to compress the permit critical path.
L-02 · Corporate
ShA covers share transfers, board composition, reserved matters, drag-along, tag-along, and the Costco-Manager firewall (Clause 14) on a standby basis per §A.10 contradiction-2.
FG-04 · Capital
VANTEC angel-syndicate equity raise replacing the suspended Class B Costco-Manager tranche per §A.10 contradiction-2. Pitch event Sep/Oct 2026.
FG-BCSRIF · Capital
BCSRIF application ($1.0–1.5M, 90% cost-share, anchor). FCC senior term debt ($400–1,000K). CALAP equipment loan ($350K, federally guaranteed). All three submitted in the same window.
CFIA-5670 · Regulatory
Aquatic-animal import permit application for live Pacific White Shrimp postlarvae from American Penaeid SC. Includes the CFIA pre-clearance letter (KILL-1) and AIRS pre-shipment check protocol.
HR-TECH · Team
Aquaculture Technician I (×2, $24/hr, M-1 and M+2). Aquaculture Technician II — WQ + Harvest cross-trained ($28/hr, M+3). Brings the Phase 1 team to its 5-FTE configuration.
OPS-TI · Site
Tenant improvement to leased ex-cannabis M-2 facility: process water + electrical upgrade + radiant heat + biosecurity rooms + quarantine raceway + cold-chain dock. Designed for ZLD from detailed-design stage.
Month 6 – 12
2026-12-15 to 2027-06-15
FACILITY-LIVE · Operations
Tenant improvement complete. Atarraya flat-packed Air Shrimp Boxes assembled on-site. Local-mode firmware tested for ≥72-hour autonomous operation. First biofloc cycle started.
CFIA-PL-RECEIVE · Regulatory
First PL shipment from American Penaeid SC under CFIA Form 5670. PCR pre-stock panel (IHHNV, WSSV, EHP, EMS) clears in the quarantine raceway before transfer to production tanks.
CHEF-SAMPLE · Sales
Live HOSO samples to Vancouver white-tablecloth restaurants + Cantonese banquet operators. First branded chef-only tasting event in Richmond. Live-channel time-to-revenue 1–3 months from first harvest.
TT-PILOT · Sales
Asian retail live-tank pilot at T&T Richmond. Lunar New Year window-test deferred to Month 19 (Jan 2028). H-Mart Coquitlam secondary qualified in parallel.
FIRST-REVENUE · Sales
First chef sale closes 12 months from term-sheet signature. Restaurant + Asian retail channels run as Phase 1 anchors — no certification gate, $14–22/lb wholesale, 1–3 month time-to-revenue.
COSTCO-PQ · Sales
Costco Canada Pre-Qualification Request submitted at M-8 (per DeepSeek finding on RSP Shrimp Policy timing; source needs verification). Establishes vendor profile, GDST traceability roadmap, and BAP / ASC certification trajectory ahead of Phase 2 Roadshow window.
BAP-3STAR-PREASSESS · Regulatory
BAP 3-star pre-assessment with SAI Global or equivalent licensed BAP auditor. DeepSeek finding flags that Costco RSP Shrimp Policy may require BAP 3-star (not 2-star) for raw shrimp DC delivery (source needs verification — DeepSeek constructed-citation flag pending Costco Canada Supplier Portal confirmation).
Month 12 – 18
2027-06-15 to 2027-12-15
PROD-RAMP · Operations
All 20 boxes in steady-state biofloc cycle. Phase 1 saleable lb ramps to ~58,000 lb Y2 at the Expected blended ASP of $13.50/lb.
SFC-LICENCE · Regulatory
SFCR-compliant Preventive Control Plan (live + frozen CCP branches) reviewed and approved by CFIA. 3–4 month application-to-licence cycle.
GFSI-AUDIT · Regulatory
Stage 1 GFSI-benchmarked audit (target: BRCGS Issue 9). SQF and FSSC 22000 evaluated as alternatives if cycle timing favours either. Certification body engaged Month 10.
CHEF-30 · Sales
Chef channel scaled from 5 anchor accounts to 30+ active accounts across Metro Vancouver. Restaurant channel volume target 8,000–12,000 lb/yr at $14–18/lb.
ASIAN-RETAIL-8 · Sales
T&T Richmond + H-Mart Coquitlam + 6 independent live-tank grocers across Metro Vancouver and Surrey. Lunar New Year window (Jan/Feb 2028) tests the 15–25% live-segment uplift.
BCSRIF-T2 · Capital
BCSRIF reimbursement-based disbursement against Phase 1 certification + commissioning milestones. Reduces working-capital pressure ahead of the Phase 2 gate evaluation in Year 3.
Section E — unified spec
A Phase 2 raise of approximately $8–12M CAD is permitted only if all five gates below are met. If any one gate fails, Phase 2 is deferred 12 months and re-evaluated against the cap-and-license economics. Two further gates are advisory.
P2-1
P2-2
P2-3
P2-4
P2-5
P2-6
AdvisoryP2-7
Advisory18-month critical path
Sixteen of the highest-signal milestones over the first eighteen months. KILL gates in red — any one of these negative halts the project. Verification gates in ochre. Standard milestones and financing tranches in the navy palette.
Open gates
Every on the list below is an open question whose answer must land before the next commitment. The full cross-module risk register lives at /risk.
| ID | Gate | Target | Status |
|---|---|---|---|
| V-01 | BC mech-eng heat-load study (gates LOI) | Day +21 | Open |
| V-02 | Atarraya term sheet with 5 mandatory asks | Day +30 | Open |
| V-03 | CFIA AIRS + Form 5670 dry-run (KILL-1) | Day +90 | Open |
| V-04 | BCSRIF eligibility re-verification (anchor instrument) | Day +14–30 | Open |
| V-05 | Costco April 29 verbatim debrief | overdue → Day +37 | Open |
| V-06 | Lease comps verified on three M-2 sites | Day +44 | Open |
| V-08 | BC Hydro rate-schedule classification at site | Day +60 | Open |
| V-10 | Per-account weekly volume model (5-chef phone canvass) | Day +30 | Open |
| G-2 | Holding structure: sibling CCPC, not under 1362557 | Day +24 | Open |
| G-3 | Phase 2 gating criteria documented (Section E) | Day +45 | Closed |
| G-7 | KILL-gate weekly tracker dashboard live | Day +14 (then weekly) | Open |
| G-8 | Long-game exit articulation (held / sold / licensed) | Day +120 | Open |
Full Section D open-gates timeline (50+ items) → /risk register
Three bright lines
We update the open-gates table on this page and the milestone tracker every two weeks. Subscribe for milestone updates and the quarterly investor briefing.
Cross-links: /risk register · /financials · /regulatory · /team